Free in the browser; try it without an account. To save, export and share, create a free account.If you build now and buy the solar system or the wallbox later, lay the conduits in the shell: a conduit in the screed or the wall costs a few euros a metre, a cable route through finished rooms later costs many times that. As a guideline for a detached house: from the roof to the plant room two M32 for the modules' direct current cables and one M25 for data, from the distribution board to the parking space one M40 for the wallbox supply and one M20 for its data cable. In Germany, new residential buildings with more than five parking spaces must equip every space with cable infrastructure under the GEIG. All figures are guideline values for orientation; the work belongs in the hands of a registered electrical contractor.

Detached house with basement
228.1 m² · 17 rooms
Which conduits for PV and a wallbox?
| What for | Cables (example) | Conduit (guideline) |
|---|---|---|
| PV direct current, 2 strings | 4 × solar cable 6 mm², each about 6.5 mm thick | M32, better 2 × M32 with spare |
| PV data (inverter, meter) | Cat 7 or bus | M25 |
| PV alternating current to the meter cabinet | NYM-J 5 × 2.5 | M25 |
| Wallbox supply 11 kW | NYM-J 5 × 6 (about 15.5 mm thick) | M40 (M32 only short and straight) |
| Wallbox supply, long run | NYM-J 5 × 10 (about 19.5 mm thick) | M40 |
| Wallbox data (load management) | Cat 7 | M20 |
| Parking space outdoors | NYY cable in the ground | cable protection pipe DN50 |
Behind it is the rule of thumb for fill: the cables should fill at most about 40 % of the conduit's cross section, and the inner diameter should be at least 1.5 times the thickest cable. With more than two bends or over 15 m, take one size up. The conduit size calculator works it out for your own cables.
The route from the roof to the plant room
The direct current cables enter the house at the roof cable entry and run to the inverter, usually in the plant room or the basement. Two routes are common:
- Inside: from the roof entry through the loft and down a shaft, a disused chimney or a continuous conduit. Protected and out of sight, but easy to lay only in the shell.
- Outside: down the facade in a UV-resistant conduit or duct, through the wall only close to the inverter. Good for retrofitting.
Keep the direct current route inside the house short and plan it with your electrician. Put direct current, alternating current and data in separate conduits; where they cross, preferably at right angles. A pull wire in every conduit makes pulling cables in easy later, even if the conduit stays empty for years.
Wallbox and the GEIG
For the wallbox you lay the supply from the distribution board or the meter cabinet to the parking space, and next to it a data conduit for load management or charging with PV surplus. How thick the supply gets depends on power and length; your electrician decides. An M40 leaves room for the thicker cross section.
The German Building Electromobility Infrastructure Act (GEIG) requires cable infrastructure, "all cable routes to take electrical and data cables", conduits for example:
| Case | Duty under the GEIG |
|---|---|
| New residential building, more than 5 spaces | every space (§ 6) |
| New non-residential building, more than 6 spaces | every third space and at least one charging point (§ 7) |
| Major renovation, residential, more than 10 spaces | every space (§ 8) |
| Major renovation, non-residential, more than 10 spaces | every fifth space and one charging point (§ 9) |
The GEIG does not apply to a detached house with a garage and a carport; preparing still pays. Check the current version of the act before planning; the EU buildings directive tightens the rules.
Every wallbox is registered with the grid operator before it goes into service. If the charging equipment adds up to more than 12 kVA, for example a 22 kW wallbox, it needs the operator's consent beforehand (§ 19 NAV). Wallboxes over 4.2 kW are also controllable consumers under § 14a EnWG.
How to plan it in RoomPlanning
- Place the roof cable entry, the distribution board, the media enclosure and the wallbox at the parking space from the catalog under Electrical & services; an inverter too, if you know it already.
- In the Conduit tool, choose Propose conduit network and the trades Photovoltaics and Wallbox. RoomPlanning lays 2 × M32 direct current and 1 × M25 data from the roof entry, and M40 and M20 from the distribution board to the wallbox (Plan conduits).
- The Hints then name, for example, conduits too full, power and data in the same conduit, a bend radius too small or parking spaces without a conduit under the GEIG.
- The bill of materials gives the metres per size, the boxes and penetrations, the conduit plan shows the routes for the shell (Conduit plan and bill of materials).
The modules themselves, yield, battery and the wallbox's consumption are planned under Plan a solar PV system.
Frequently asked questions
Is a conduit worth it if the PV system comes years later?
Yes. In the shell a conduit costs little; later a cable route has to go through finished walls and slabs or along the facade. An empty conduit with a pull wire keeps both open: the solar system and the wallbox, but also a later heat pump or battery.
How many conduits do I need from the roof?
For a detached house with one or two strings, two M32 for direct current and one M25 for data are usually enough. With several roof faces or module inverters your electrician may plan differently; a spare conduit never hurts.
Do I have to prepare a detached house under the GEIG?
No. The duties apply to residential buildings from six parking spaces and to non-residential buildings from seven. For a detached house preparing is voluntary, but cheap.
May I connect the wallbox myself?
No. You may plan it yourself; a registered electrical contractor connects it and registers the wallbox with the grid operator.
Sources
Guideline values for planning, not legal or engineering advice. Read on 16 November 2026:
- Cable infrastructure and parking spaces: Gebäude-Elektromobilitätsinfrastruktur-Gesetz (GEIG), §§ 2, 6 to 9
- Registering charging equipment: § 19 NAV
- Controllable consumers: § 14a EnWG
- Cable routes for solar cables: photovoltaik.info, Kabelwege und Leerrohre für Solarkabel planen
- Planning electrical installations in homes: DIN 18015-1 (PDF), elektro.net