Creating an electrical plan: a guide with installation zones
Last updated: 16 November 2026
Try it right away
Free in the browser; try it without an account. To save, export and share, create a free account.An electrical plan shows in the floor plan where sockets, switches, lights and connections are and which circuit they are on. You create it in five steps: lay out the floor plan with furniture, decide what each room needs, place the symbols in the installation zones, form circuits and print the plan with a legend. Such a plan is the best basis for talking to the electrician. In Germany, though, only a registered electrical contractor may install the system and connect it to the grid.
In the Detached house 140 m² the electrical plan is already drawn: switches, lights, sockets and smoke detectors on both storeys, every room on its circuit.

Detached house 140 m²
143.4 m² · 13 rooms
Step 1: Floor plan with furniture
Plan the electrics only once it is clear where the bed, sofa, TV, desk and kitchen will go. A socket behind the wardrobe is no use to anyone, and a light switch on the wrong side of the door annoys you every day. So draw the floor plan to scale with doors, windows and furniture first (How to draw a floor plan).
Step 2: Decide what each room needs
How many sockets, light points and data connections a room needs at least is set in Germany by DIN 18015-2. Above that, the guideline RAL-RG 678 describes standard and comfort equipment with two and three stars. The tables are in the guide How many sockets per room?, and for a single room the sockets calculator works it out.
For each room also note what needs a connection of its own: cooker, oven or steam oven, dishwasher, washing machine, dryer, instantaneous water heater, roller shutters, outdoor lights, network and a possible electric car charger.
Step 3: Place the symbols
Installation plans use the graphical symbols of DIN EN 60617-11. The most important:
| Symbol | what for |
|---|---|
| socket, earthed | a socket for one appliance; several side by side as a multiple socket |
| one-way switch | switch a light on and off from one place |
| double switch | switch two lights or groups of lights separately from one place |
| two-way switch | switch a light from two places, such as both ends of a hallway |
| intermediate switch | with two two-way switches: a light from three or more places |
| push button | switches through a relay or smart home system, also from many places |
| light, ceiling outlet | connection for a light on the ceiling or wall |
| junction box | box in which cables are connected |
Put a switch at every room entrance, a separate one at each bed, and one for the stair light on every storey.
Step 4: Keep to the installation zones
Under DIN 18015-3, cables in the wall run only in defined zones, horizontally or vertically. Anyone who later hangs a picture or drills for a shelf then knows where not to drill.
| Zone | Position |
|---|---|
| top | 15 to 45 cm below the ceiling, at most 30 cm wide |
| bottom | 15 to 45 cm above the floor, at most 30 cm wide |
| middle | 100 to 130 cm above the floor, only in rooms with worktops on the wall, such as the kitchen and utility room |
| vertical at doors | 10 to 30 cm beside the structural edge, at single doors on the lock side |
| vertical at windows and corners | 10 to 30 cm beside the structural edge or corner |
The centre of each zone is the usual place for cables and boxes: 30 cm above the floor, 30 cm below the ceiling and 15 cm beside doors, windows and corners.
Usual heights:
- Sockets: 30 cm above the finished floor.
- Switch beside the door: 105 cm above the finished floor.
- Above the worktop: in the middle zone, often around 115 cm.
- Barrier-free to DIN 18040-2: switches and controls at 85 cm.
Step 5: Form circuits
A circuit is everything behind one fuse. For lights and general sockets DIN 18015-2 gives the minimum by floor area: 3 up to 50 m², 4 up to 75 m², 5 up to 100 m², 6 up to 125 m² and 7 above. The cooker, microwave or steam oven, dishwasher, washing machine, dryer, water heaters and the car charger each get a circuit of their own, the cooker on three-phase power. With standard and comfort equipment every larger room has a circuit of its own. If a fuse trips, the rest of the home stays on.
Protection: sockets up to 32 A and all lighting circuits in homes need a residual current device (RCD) of at most 30 mA (DIN VDE 0100-410). An arc fault detection device (AFDD) is not a general requirement. For circuits in bedrooms, though, DIN VDE 0100-420 requires a risk assessment, and the AFDD is one possible measure there.
Distribution board: in an apartment with several rooms the board has at least four rows. Leave room for later, Hager recommends about 20 % spare.
Special case: the bathroom
In the bathroom there are zones around the bath and shower (DIN VDE 0100-701). Under the 2008 edition, zone 1 above the bath or shower reaches 2.25 m high, and zone 2 adjoins it 60 cm wide. Ordinary 230 V sockets are not allowed in either zone. A new edition has applied since June 2025, with a transition period to the end of 2027, and it changes some rules. So clarify with the electrician what may go where in the bathroom.
Drawing the electrical plan in RoomPlanning
- Choose the Electrical tool with E and pick a symbol: sockets, switches, ceiling outlets, network sockets, smoke detectors and more.
- Place symbols: click in the plan. On walls they align themselves. Hold Shift to place several in a row.
- Set up a circuit: on the right New circuit, give it a name, then draw the cable from symbol to symbol. With A the next section becomes an arc, as in many installation plans.
- Check: every circuit has its own colour. On the right you see how many symbols are on each. Afterwards you plan the conduits to the boxes with the Conduit tool (Plan conduits); for PV and a wallbox see Conduits for PV and a wallbox.
- Print: Print electrical plan prints walls, rooms, symbols and cables with a legend: every circuit with the number of its symbols and the length of its cables. You can also put the legend on a sheet with the floor plan and sections (Drawings and export).
The full guide with pictures is under Planning circuits. The electrical plan applies per storey, so for a house you switch to the upper floor and carry on there.
Frequently asked questions
May I create an electrical plan myself?
You may plan and draw it yourself, and a good plan saves time and money with the electrician. In Germany, however, work on the installation behind the house connection may only be done by the grid operator or by a contractor entered in a grid operator's register of installers (section 13 NAV).
At what height do sockets and switches go?
Sockets usually 30 cm above the finished floor, switches beside the door at 105 cm, above the kitchen worktop often around 115 cm. Barrier-free, switches sit at 85 cm.
How many circuits does a home need?
For lights and sockets at least 3 up to 50 m² and one more for every further 25 m², at most 7 from 125 m². On top come the circuits for the cooker, dishwasher, washing machine and the other large appliances.
Which symbols are used in an electrical plan?
The graphical symbols of DIN EN 60617-11, for example for socket, one-way switch, two-way switch, intermediate switch, push button and light.
Sources
- RAL-RG 678, Kurzfassung (PDF, 2023) – HEA (German)
- Hager Tipp 21: DIN 18015 (PDF) – Hager (German)
- Leitungsverlegung und Installationszonen – Baunetz Wissen (German)
- Elektroinstallation in Räumen mit Badewanne oder Dusche – Baunetz Wissen (German)
- DIN VDE 0100-701:2025-06 – DIN Media (German)
- DIN VDE 0100-410: protection against electric shock – Hager (German)
- Brandschutzschalter – Baunetz Wissen (German)
- DIN EN 60617-11 – DIN Media
- Planungsgrundlagen barrierefreies Bauen (PDF) – Bavarian Ministry of Housing (German)
- § 13 Niederspannungsanschlussverordnung (NAV) – gesetze-im-internet.de (German)
This guide is general information and does not replace planning by a qualified electrician.