Plan conduits
Step by step on the detached house: show the installation zones, draw conduits in the floor to the boxes, check cables, fill and size, read the hints and see the conduits in 3D.With the Conduit tool you plan where conduits for power, data, PV, a wallbox or the garden run: in the floor on the raw slab, in the installation zones of the wall or at the ceiling. This guide shows it on the Detached house 140 m² without building services (the template in the gallery has them drawn in already): you run two conduits in the floor from the media enclosure in the utility room to the network sockets in the study. It takes about ten minutes.
Open the template in the editor1. Place boxes and devices
First place sockets, switches and lights with the Electrical tool (Planning circuits) and network sockets and distributor with Network & smart home (Plan a network). In the catalog under Electrical & services you find what a conduit network needs:
- Junction box and flush box, each for solid and for hollow walls, and pull box;
- Surface junction box, concrete ceiling box and floor box;
- Multi-utility house entry, roof cable entry, wall sleeve and ceiling sleeve;
- Garden socket post.
In the example a media enclosure hangs in the utility room, and two network sockets sit in the study, one on the wall to the utility room and one on the outer wall.

- Network sockets
- Media enclosure
2. Show the installation zones
Open the Layers section at the bottom right and switch on Installation zones with the eye; they start switched off. The floor plan then shows the vertical zones beside doors, windows and wall corners and the band at the ceiling. The wall view also shows the horizontal zones. The zones follow the German standard DIN 18015-3; their sizes and what the hints check about them are in Installation zones.

- Switch on installation zones
- Zones at the wall
3. Pick the Conduit tool
The tool is in the left bar under Building services. Pick Conduit. In the Conduit section on the right you set what the next conduit will be:
- Level: Floor (on the raw slab), Lower zone, Upper zone or Ceiling; the zones put the conduit on their preferred line;
- Trade: power, data (network), satellite/aerial, fibre, bus (smart home), PV direct current, PV alternating current, wallbox, outdoor, speaker, security or spare;
- Size: by trade, or M16 to M63, for the ground cable protection pipes DN50 to DN110;
- Conduit type: to suit where it lies (in the floor corrugated medium 750 N), or corrugated light (320 N), corrugated medium (750 N), rigid, cable protection pipe or UV resistant;
- Pull wire: whether a pull wire lies in the conduit.
In the example you choose Floor and the trade Data (network); the size follows from it (M25).

- Conduit
- Level
- Trade, size, conduit type, pull wire
4. Draw conduits
Click from point to point on the plan. A conduit lies in the floor on the raw slab, in a zone of the wall or at the ceiling. Sockets, switches and boxes catch the conduit: when it ends at a box, its end sits exactly there and a vertical stub runs to it. A double click or Enter ends the conduit. In the wall, run conduits only horizontally or vertically (with Shift). For a box outside the zones, draw a vertical stub from the nearest horizontal zone.
In the example both conduits start in the floor in front of the media enclosure and each ends at a network socket. Every conduit gets a label from trade, storey and number, for example "D-EG-01".

- Two conduits in the floor
- Trade data
5. Cables, fill and size
A click with Select on a conduit selects it. On the right you change label, trade, size and conduit type. Under Cables you see the cables with their Count; the conduit brings one cable of its trade, Add cable adds more. Below are the fill, the length and the number of bends. Suggest size sets a size that fits the cables.
As a guideline, the cables should fill at most 40 % of the cross section. With more than two bends or over 15 m you need a pull box or one size more. In the example two Cat 7 cables and one NYM-J 3×1.5 lie in the conduit: the conduit is too full, and power and data do not belong in the same conduit.

- Cables
- Fill
- Selected conduit
6. Read the hints
Pick Conduit again. In the Hints section RoomPlanning checks your conduits against guideline values, for example:
- a conduit in the wall outside the installation zones;
- a box outside the zones without a vertical stub;
- a fill above 40 %;
- more than two bends or more than 15 m without a pull box;
- a bend radius too small for a cable;
- power and communication in the same conduit;
- a conduit type not fit for concrete, screed, the ground or outdoors;
- a ceiling conduit closer than 20 cm to a wall.
A click on a hint shows the spot on the plan. Hints block nothing; they are suggestions for the talk with the electrician.

- Hints with their source
7. See the conduits in 3D
In the 3D view, switch Building services on the right to X-ray: then you see the conduits in the floor, in the walls and at the ceilings, together with the other pipes. With the walls on Cut and Walls towards the camera see-through the view is clear.

- Building services: Off, Visible, X-ray
8. Walls, lintels and floor build-up
Whether a chase is allowed depends on the wall. Select a wall and set its Structure (masonry, concrete, drywall, timber studs) and whether it is Load-bearing; for doors and windows, Own lintel takes the lintel height and bearing. The floor build-up is set on the storey (Floor build-up). The hints then also check the structure after DIN EN 1996-1-1/NA; what exactly is in Installation zones. On top come conduits in the heated screed, crossings with water pipes, conduits too shallow in the ground, open ends and parking stalls after GEIG.
9. Propose a conduit network
Place network and TV sockets, a media enclosure, the distribution board and, if you like, a wallbox, a roof entry and garden sockets. Then open Propose conduit network in the Conduit tool, choose the trades and apply: star-shaped conduits in the floor through the doors, an M25 from every socket to the media enclosure, 2 × M32 between storeys, PV, wallbox, garden and reserve. It is one step you can undo. Boxes that already have a conduit stay as they are.
10. Bill of materials and shell documents
The Conduit bill of materials shows the sums (metres, boxes, conduits); Open bill of materials shows the whole list as CSV or Excel. Under Shell documents you print the storey's conduit plan and the labels and create the sheet set "Shell electrics". How that works and what the wall view, room elevations, bill of materials and DXF export hold is shown in Conduit plan and bill of materials.
In the 3D view, Building services: Shell shows conduits and boxes without furniture in a see-through house. With Installation zones of the storey as bands the zones of the chosen storey appear as light, translucent bands on the walls and under the ceiling (the same switch as the layer in the floor plan). A GLB export carries the conduits only when you choose Export conduits; they are then in a node of their own, “Conduits”.
Good to know
- The conduits lie on the Conduits layer, the zones on the Installation zones layer. Under Layers you hide and show them.
- Conduits belong to the storey you draw them on (Levels).
- Drawing, zones, hints, wall views, room elevations and the 3D shell view are free. The bill of materials with CSV and Excel, the lists on sheets, the sheet set, the labels and the proposal (free once per plan to try) come with Premium.
More guideline values on zones, conduit sizes and fill are under Plan conduits and installation zones. Water and drains are planned under Plan water and drains.